Punch List Template

This is a closeout punch list you can copy and fill in — one row per defect, with the location, the trade responsible, the date it was raised, the date it was fixed and a place for both parties to sign it off. Walk the job with it rather than emailing it afterwards.

Last reviewed 9 Sept 2026

Free to use. No email, no sign-up. Paste it into Word, Google Docs or an email and replace anything in [BRACKETS].

Punch List

Project

Project: [PROJECT NAME / ADDRESS]
Owner: [OWNER NAME]
Contractor: [CONTRACTOR NAME]
Walkthrough date: [DATE]
Attendees: [WHO WALKED THE JOB]
Target completion of all items: [DATE]
Set one date for the whole list. Open-ended punch lists never close.

Items

One line per defect. Be specific about location — 'paint touch-up, master bedroom, east wall behind door' can be found; 'paint issues' cannot.

#LocationItem / defectTradeIdentifiedCorrectedVerified by
1Kitchen — sink baseCabinet door out of alignment, rubs frameCarpentry[DATE]
2Kitchen — backsplashGrout haze on tile above rangeTile[DATE]
3Master bathGFCI does not reset; no power to vanity outletElectrical[DATE]
4Master bath — showerMissing sealant at pan-to-tile joint, left cornerTile[DATE]
5HallDrywall nail pop, ceiling near attic hatchDrywall[DATE]
6Living roomWindow sash binds, will not lockWindows[DATE]
7Exterior — north sideDownspout not connected to extensionGutters[DATE]
blankblankblankblankblankblankblank
blankblankblankblankblankblankblank
blankblankblankblankblankblankblank
blankblankblankblankblankblankblank
blankblankblankblankblankblankblank
blankblankblankblankblankblankblank
blankblankblankblankblankblankblank
blankblankblankblankblankblankblank

Items by room

If it is easier to walk room by room, repeat this block per room and leave the rows blank.

Room: [ROOM NAME]Item / defectTradeCorrectedInitials
blankblankblankblankblank
blankblankblankblankblank
blankblankblankblankblank
blankblankblankblankblank
blankblankblankblankblank
blankblankblankblankblank

Outstanding documents

These belong on the punch list too — they are as much a part of closeout as a sticking door.

- Final inspection sign-offs / certificate of occupancy
- Manufacturer warranties and registration for installed equipment
- Operation and maintenance manuals
- Final unconditional lien waivers from contractor and all subcontractors and suppliers
- As-built drawings or marked-up plans where applicable
- Touch-up paint and spare material (tile, flooring) left on site
- Keys, remotes, access codes and filter sizes

Sign-off

All items listed above have been completed to the satisfaction of the owner, except any item noted as outstanding below. Signing this list does not waive the contractor's warranty obligations or the owner's rights in respect of latent defects that could not reasonably have been seen at the walkthrough.

Items remaining open: [LIST OR 'NONE']

Owner signature: ___________________________  Date: ____________
Printed name: [OWNER NAME]

Contractor signature: ______________________  Date: ____________
Printed name: [CONTRACTOR NAME]

Final payment of $[AMOUNT] is due upon completion of every item on this list and delivery of final lien waivers.

Free to use. No email, no sign-up. Paste it into Word, Google Docs or an email and replace anything in [BRACKETS].

How to use this template

A punch list is a closeout document, not a complaint list

The distinction matters, and it changes how the document is received.

A punch list is the short list of incomplete or defective items standing between substantial completion and final payment. It is a normal, expected part of finishing a job — every project has one, and a good contractor is waiting for it so they can close the file and get paid. Written that way, it gets worked through.

A list written as grievances gets defended against. Same items, different reception. Describe the condition and the location, not the failure of character: "grout haze on tile above range", not "tile guy rushed the backsplash". You want the item fixed, not an admission.

Keep it to work that is genuinely incomplete, defective, or not what the contract called for. Things you have changed your mind about are change orders, not punch items, and mixing them in is the fastest way to lose credibility on the whole list.

Walk it with the contractor, do not email it

An emailed list arrives as a verdict. A list built while walking the house together becomes a shared to-do.

There are practical reasons beyond tone. Half the items get resolved on the spot — a switch you thought was dead is on a different circuit, a mark you thought was a defect is a shadow, a door that binds gets adjusted while you are standing there. The rest get clarified: you point at the exact spot, they see what you see, and nobody spends a week fixing the wrong thing.

Bring a phone and photograph every item as you go, with something in the frame for location. Number the photos to match the row numbers. Photos end most of the disagreements about whether something was already like that.

Go at the right time. Walk once at substantial completion, in daylight, with the power on and the water running. Bring a flashlight, hold it flat against walls to rake the light across drywall and paint, and check every outlet and switch. Open and close every door and window. Run every fixture and look under every sink while it drains.

Tie final payment to it, and hold enough back

This is the only leverage that reliably works.

Once the last payment is gone, a punch list becomes a favour. The crew is on another job, the trades have moved on, and the small stuff — the sealant, the missing register cover, the one cabinet door — stretches out over weeks of unreturned calls. Nobody is being malicious. It is simply that unpaid work is not scheduled work.

Hold 5 to 10% of the contract until the list is closed. Say so at contract signing, not at the walkthrough, and write it into the payment schedule so nobody is ambushed. The amount has to be worth coming back for: on a $60,000 job, $500 will not bring a crew back across town, and $4,000 will.

Set a completion date for the whole list at the walkthrough, and set it in the document. "As soon as we can" produces an open list six months later.

What is not a punch item

Latent defects — the ones you could not have seen at the walkthrough — are warranty items, not punch items. A leak that shows up after the first hard rain, a floor that cups in month three. Do not fight to squeeze those onto the punch list; note in the sign-off that signing the list does not waive warranty obligations, and handle them under the warranty when they appear.

Normal settling cracks, hairline drywall lines at joints in the first year, and minor nail pops are usually covered by a one-year callback rather than final payment. Most contracts spell that out. Read that clause before the walkthrough so you know which pile each item goes in.

Frequently asked questions

What is a punch list in construction?
The list of incomplete or defective items identified at substantial completion, which the contractor must finish before the job is closed out and final payment is released.
Who creates the punch list?
On residential work, the owner and contractor walk it together. On commercial jobs the architect or owner's representative issues it, often after the contractor submits their own pre-punch. Either way, one written list, agreed by both sides.
How long does a contractor have to complete a punch list?
Whatever the contract says — commonly 14 to 30 days. If it says nothing, agree a date at the walkthrough and write it on the list. An undated punch list drifts indefinitely.
How much money should I hold back for the punch list?
Five to ten percent of the contract is standard, and it needs to be enough to be worth returning for. Agree the retainage when you sign, not when you walk.
Can I add items after the walkthrough?
Genuine defects you missed, yes — reasonably and promptly. Changes of mind are change orders. Continually adding to the list after the fact is the surest way to lose the contractor's cooperation on the items that count.
Does signing the punch list end the warranty?
No. Sign-off means the listed items are done. Warranty obligations and rights over latent defects continue under the contract, and the sign-off block on this template says so explicitly.